| Home
> Ask the Engineer
> Structural Evaluations
Structural Evaluations
By Stephen
Varone, AIA and Peter Varsalona, PE
My apartment in a pre-war
cooperative shares a lot line with an adjacent property on which a new
building is being constructed. (Our building abutted the now demolished
building that was on the site.) Hairline cracks have started appearing in
my bedroom wall and so has a new gap between the wall and the floor. Our
superintendent says he also notices new cracks in our basement on the same
side of the building. The board is worried that the construction next door
is causing these conditions and that they could worsen as time goes on,
especially given that our building is old and the exterior walls have not
been maintained that well over the years. How do we determine if the
construction next door is to blame for the cracking walls and gap, and
what should we do in the meantime?
Damage from adjacent construction work is an
all-too-common problem, and older buildings with potentially weaker walls
such as yours are particularly vulnerable. Although the responsibility for
protecting surrounding properties rests with the developer/owner of the new
project, it behooves boards to take precautionary steps when construction is
planned next door.
Pre-construction Survey
One strongly recommended measure is to have a survey conducted of the
building before any demolition or excavation begins next to it. A
pre-construction report serves as a record of the building’s overall
structural condition, which the board can then use as a baseline to compare
against any new damage that may be subsequently caused by the adjacent
construction. |
| In a pre-construction
survey, an engineer visually inspects the building’s exposed structural
elements, including the foundation, exteriors and interior walls, floors,
columns, beams, joists, lintels, and even roof level components such as
parapets and bulkheads. The condition of these elements and walls adjacent
to the construction is obviously of particular importance. In addition to
observing the physical property, the engineer reviews the developer’s
demolition and construction plans to determine if the proposed work follows
the proper methods, conforms to building code, and adequately protects the
buildings next to it. |

Construction work can cause structural damage to adjacent buildings,
especially older ones with weaker walls. |
|
To establish proof of pre-construction conditions,
the engineer should take plenty of photos throughout building. The more
detailed and thorough the report (especially the photographic
documentation), the stronger the board’s case will be should damage occur.
Even if a survey was not conducted before construction began (as in your
building’s case), it does not mean that it’s too late to have one performed
now. It’s still important to document the damage that you think may have
been caused by the construction work next door, so it’s recommended that the
board undertake a survey as soon as possible before any further problems
develop.
Problem Signs
Obvious problems that an engineer conducting a survey would look for are
shifted walls; cracked, loose, or spalling bricks; deteriorating mortar
joints; loose or missing coping stones; deteriorated or missing base
flashing or counterflashing on the roof, deflected lintels and relieving
angles; and improperly spaced or non-existent expansion joints. Some of
these conditions may be structural in nature, while others could be the
result of water penetration, which in turn can slowly wreak havoc on a
building and lead to structural problems if not addressed.
Inside the building, the engineer looks for cracked or bulging walls,
sloping or sagging floors, gaps between walls and floors or walls and
ceilings, rotted or defective joists or beams in the basement, and any
out-of-plumb structural elements.
If the survey identifies structural deficiencies, the next step would be for
the engineer to perform tests to determine the extent of the damage. One way
is to sound out areas by lightly tapping a hammer to detect soft spots or
loose material. The engineer may also want to conduct investigative probes
of problem areas by having a contractor remove a small section
(approximately one square foot) of surface brick or masonry to better
determine underlying conditions. Depending on the condition of the wall,
several or more probes could be in order.
Shaky Foundation
Because the former building on the adjacent site abutted your cooperative,
chances are both buildings shared the same foundation wall (also called a
party wall). If so, it is possible that the building’s demolition and the
subsequent excavation have had an adverse effect on your building.
Vibrations from demolition of the adjacent building, for example, could have
been transferred to your wall. In addition, removing soil next to the
foundation wall—especially if the digging went deeper than your
basement—could have caused your building as a whole to shift and settle.
Given the age of your building, the foundation wall is probably the standard
stone-rubble type of the pre-war era. If the existing foundation wall—your
basement wall, which now has cracks—is in poor condition, the developer of
the adjacent property should have taken precautionary steps to protect it.
One method is to pressure grout the wall by coating it with a layer of
cement, which strengthens the wall and protects it from cracking or
crumbling. The developer should have also provided temporary shoring to
support the wall and keep it from shifting. If neither of these measures
were taken, it is more likely that your building has been adversely affected
by the demolition and excavation.
According to New York City Building Code, a new building being erected
cannot bear on an existing party wall but instead must rest on a new
foundation wall, usually made of reinforced concrete. There should be a
space between the two walls, typically filled with a foam material, to keep
loads from transferring from the new to the existing building. In addition,
if the new structure’s basement is deeper than the adjacent one, the
developer is required to install an underpinning below the existing
building’s basement to help prevent the building from settling.
If your building is more than six stories tall, you can also compare the
survey’s findings to the most recent Local Law 11/98 facade inspection
report. The report won’t detail conditions inside the building, but it
should have reported any major exterior defects and subsequent repairs,
which could then be evaluated in light of any defects that have become
visible since then.
Monitoring Defects
In the meantime, keep an eye on the hairline cracks in your bedroom wall and
the gap between the wall and the floor. If the cracks and/or gap become
larger, or you see signs of water penetration, bulging, or other
deficiencies, you may have to have a structural engineer investigate
further. The finished wall will likely need to be removed to examine the
underlying structure and the extent of damage. Any sheared or cracked brick
on the inside or outside face of the wall will need to be replaced. If the
damage extends beyond the immediate area, structural reinforcement measures,
such as supporting damaged beams with new beams (called sistering) might be
necessary.
The areas around the lintels (the horizontal structural elements that span
the top of window and door openings) are especially vulnerable to structural
forces, so they should be observed for any defects, such as sagging,
bulging, cracking, or leakage. The basement wall—the building’s
foundation—also bears the brunt of any additional loads on the building, so
that should be monitored daily as well.
A post-construction survey should be conducted to compare your building’s
previous condition against its condition after the demolition, excavation,
and new construction are completed. However, if the first survey clearly
shows that the developer of the adjacent property is already causing damage
to your building, exacerbating existing damage, or not following proper
building code procedures for demolition, excavation, or new construction,
your board may have to take legal action to have the work stopped.
In the meantime, the board should take the proper safeguards and make any
necessary repairs to keep the damage from getting worse and ensuring that
your building is structurally sound.
Stephen Varone, AIA is president and
Peter Varsalona, PE principal of RAND Engineering & Architecture,
PC. This column was originally published in the
September 2006 issue of Habitat Magazine.
More Ask the Engineer
articles |