|
The plumber will go through the entire system, testing the lines to
determine which lines "hold" adequate pressure and which ones
don't. If the leak is limited to just one or two areas, then usually only
those sections of piping will need replacement. But if leaks are found
throughout the system, especially in an older building such as yours,
it's usually a sign that it's time to undertake a re-piping of the entire
system.
If your plumber determines that the extent of the leaks is extensive
enough to warrant replacement of all the gas piping, the first step will
be to determine where the new gas lines are to be run. It's recommended
that the board consult with a professional engineer to ensure that the
locations of the new pipes are safe, feasible, and code compliant. In
most cases, to avoid demolition and intrude on residents as little as
possible, the existing risers (especially those running behind walls)
are left abandoned in place. Depending on the building's design and aesthetic
considerations, some boards may decide to run the new lines exposed in
individual apartments. The New York City Building Code prohibits gas piping
in public hallways and stairwells unless placed in a fire-rated enclosure
that does not block fire egress. Gas piping also cannot be run in a ventilation
shaft; however, a legally abandoned dumbwaiter or elevator shaft would
be permissible. Installing piping outside the building is also permitted
but tends to be prohibitively expensive.
Once the location of the new piping has been determined, the lines are
installed, usually starting with the large mains and risers, followed
by the branch lines to individual apartments. Each length of new piping
is pressure tested as it is installed to avoid the complications of trying
to detect leaks only after the entire system is rebuilt. The pressure
tests are typically performed to meet a standard higher than that set
by the New York City Department of Buildings (DOB) so it will pass inspection
when the final test is conducted after the re-piping is complete.
The new system should be designed with isolation valves, which allow
the gas to be shut off to dedicated lines while leaving others intact.
These valves will avoid the need to shut down the entire system if leaks
arise in the future. Older systems such as the one in your building usually
do not have isolation valves but instead have only one main valve from
the utility. In this set-up, when there's a leak in any section the entire
system has to be shut down. Any new piping behind walls or enclosures
must have access doors so the valves can be reached. Finally, a booster
pump may be required if your building requires high-pressure gas but only
low-pressure gas is available from the utility.
Filing Drawings
A set of design drawings detailing the layout of the piping and
associated components needs to be maintained by the engineer and/or plumber.
These drawings are filed with the DOB before the project begins, along
with application forms that provide a description of what will be demolished,
removed, and installed. In some instances, after the project is completed,
an amended set of drawings (i.e., as-built plans) and forms may be resubmitted
to the DOB with revisions to reflect any changes that took place during
the course of the project. (For landmark-district properties, approval
must also be obtained from the Landmarks Preservation Commission.)
Once the new gas piping is fully installed, the plumber must conduct
a pressure test (typically 3 pounds per square inch) under DOB inspection
before the utility can reinstate gas service. The DOB inspector will also
evaluate the condition of old piping (if any remains), how the new piping
is installed, and whether everything complies with code, such as proper
fireproofing where required. To enable the inspector to thoroughly check
the system, new pipes cannot be concealed or painted until after the inspection.
Unfortunately, it can take up to six months from the time a gas leak
is detected until new piping is put in place, the system passes DOB inspection,
and the utility can turn gas service back on. During this interval, buildings
with dual-fuel systems can operate on oil for heating. (For buildings
with oil-fired systems, the board may want to consider converting to an
interruptible-gas system as part of the re-piping project.)
One word of caution: Once the new system is up and running again, the
board should be mindful when approving a resident's renovations to an
apartment. Gas lines can be easily damaged when removing a wall, floor,
ceiling, or enclosure, so they should be treated with the same caution
during demolition as a live electrical wire.
More Ask the Engineer
articles |