The newer microprocessor-based controllers have what
are called variable frequency drives. A VFD enables smooth, fine-tuned cab
movements, starting slowly, and then maintaining a steady speed until the
cab comes to a gradual stop. Because older controllers lack VFDs, they can
result in stalling, erratic rides. Over time these rough movements place
extra wear and tear on the elevator, leading to breakdowns and frequent
servicing. In addition, older relay-based controllers are prone to gathering
fine particles generated from the DC motors typically used in aging
elevators, resulting in higher maintenance costs.
An outmoded controller may also be the cause of the
cab stopping uneven with the hallway floor. Lacking the precise actions of a
VFD-controlled system, an aging elevator’s movements are affected by the
amount of weight in the cab: With many people inside, the cab tends to stop
several inches below the hallway floor. With fewer people in the cab, it can
stop up to several inches above.
A VFD-controlled cab is designed to stop within 1/4
of an inch of the hallway floor. To assure accurate stopping, a magnetic
strip is sometimes installed along the elevator shaft. The VFD controller
reads the strip, called a level controller, to determine exactly where the
cab should stop.
Another area frequently addressed in an elevator
modernization program is what’s called the collective system. Old elevators
use a down collective system, in which the elevator makes all its requested
stops going down before its requested stops going up, regardless of who
pressed the button first. A down collective system, which has only one
hallway call button per floor, is inefficient when two or more people are
waiting for the elevator and traveling in different directions.
As part of the typical upgrade, a down collective
system is converted to a selective collective system. Selective collective
systems, which have an up and a down hallway call button, travel in the
direction of the first requested stop. After making the requested stops in
that direction, it proceeds to requested stops in the other direction.
Door Jams
The problem you’re having with sticking doors is common with old elevator
systems. Doors become creaky with age, failing to open and close properly.
In such cases, replacing the door hardware is often necessary, including the
door operator (a motor that slides the door open and shut), levers, tracks,
and hangers. Some pre-war buildings that have swinging hallway doors need
not convert to sliding doors, but the doors should be checked for loose
hinges and sagging.
The heavy-duty components that will likely need
replacement or refurbishment include the elevator motor itself, which powers
the cab up and down; the sheave and cables, which serve as a kind of pulley;
the elevator shaft; guide rails; the machine brake, which activates when the
cab stops at the requested floor; counterweights; and possibly the governor,
an emergency brake activated when the cab travels too fast. Some buildings
also have a sump pump in the elevator pit in case of flooding. Most upgrades
include refurbishing the elevator machine room, located in either the
basement or a roof bulkhead.
Undertaking a full-scale modernization of the
elevator system will probably necessitate renovating the interior of the
elevator cab at the same time. To get access at much of the “guts” of the
system, such as the shaft, guide rails, door operator, wiring, and the like,
requires removing and/or demolishing the walls, floors, and ceiling of the
cab. Some boards use this opportunity to make cosmetic changes to the cab,
installing new wall panels, door coverings, carpeting, handrails,
wainscoting, and other finishing touches.
Aside from aesthetic changes, cab upgrades must
comply with the American with Disabilities Act and New York City Building
Code. For example, the call button panel must be at a wheelchair-accessible
height and have Braille or raised numbers, and the cab must use auditory
aids such as a bell or a recorded voice indicating the elevator’s direction
and floor location. New York City Building Code requires an exhaust fan in
the ceiling, adequate lighting, and a dedicated fire call telephone. A
grille on the floor of the cab, while not required, facilitates cross
ventilation in conjunction with the exhaust fan.
Accelerated Scheduling
Because of the extensive work involved in a complete elevator upgrade, it
will be necessary to completely shut down service for the entire
installation. Therefore, boards should survey residents well ahead of time
to find out their vacation plans, verifying who will be away and for how
long. For buildings with elderly patients who travel during the winter, that
may be the best time to schedule the upgrade. In any case, it’s critical to
keep residents updated on the status of the project and let them quickly
know about any delays or problems so they can adjust their schedules
accordingly.
A single-elevator upgrade in a building such as
yours normally takes approximately six weeks. But by undertaking an
accelerated schedule of 60 hours a week (10 hours a day, six days a week)
instead of the usual 40-hour week, the contractor should be able to complete
the project within four weeks. Extending the number of hours and days in the
schedule usually works better than having separate day and night crews.
In choosing a contractor to perform the work, you
should look for specialists in elevator repairs and ask for references of
projects that the firm has done for other residential buildings the size of
yours. (You will probably want to hire a separate contractor that
specializes in interior work for remodeling the elevator cab.) Given the
importance of getting the elevator back in service as quickly as possible,
it’s advisable to include a liquidated damages clause in your agreement to
give the contractor an incentive to finish on time. It’s also recommended
that you call in an elevator consultant or engineer to initially survey the
system to determine the extent of repairs, evaluate bids from contractors,
and observe the work.
As a very rough guide, the cost of a full-scale
elevator upgrade will run approximately $15,000 per floor, per elevator.
Your agreement with the contractor should include a regular preventative
maintenance program, which usually entails twice per month visits and
servicing. (Maintenance programs are not included in the cost of the
upgrade.)
Upgrading your building’s only elevator is a major
undertaking and an unavoidable inconvenience. Managed properly, however, the
modernization project will address the everyday annoyances and potential
safety problems that the aging elevator system now presents to residents.